News | Schools | Jobs | Calendar | Directory | Employee Site
 

Home > News

District News

June 13th, 2012Emerson Court Renovation Update

The renovation of Emerson Court continues to be on schedule with Phase One being completed on April 1, 2012. The renovation is being completed in three separate Phases. Phase One includes the south wing; Phase Two the north wing; and Phase Three the two-story center court structure.

Phase One departments moved into their newly renovated home on April 5, 2012. Those departments included Business Services, Budget, Finance, Procurement, Accounts Payable, Payroll and Benefits, Human Resources, Copy Center, Mail Room, Teacher Resource Room; staff break room, and the new District Reception area. As part of Phase One, the south visitors’ parking lot and the southern portion of the central courtyard was also completed with new walkways, landscaping, and storm water drainage.

Once the Phase One move was completed, construction began on Phase Two with an anticipated completion date of August 31, 2012. Departments included in Phase Two are Student Services, MIS, Technology Resource Center, and the Professional Development Center. The main highlight of Phase Two included the protection of the District’s main computer center (MDF). This 435 square foot portion of the entire Emerson Court facility controls the District’s phones and computers for all the school campuses. Before the main roof of Phase Two was removed, a secondary weather-proof roof had to be built above the MDF to protect is from potential rain and other infiltration. The MDF remains in operation during the entire renovation effort.

Phase Three is scheduled to begin construction September 1, 2012 and will be completed by January 31, 2013.

Latest News

March 25th, 2013Annual Notice Regarding Destruction of Education Records

More...

March 20th, 2013Phoenix #1 Proud to Announce Magnet Traditional School One of 16 to Receive National Honor

More...

February 5th, 2013Historic Emerson Court Restoration Celebration

Phoenix Elementary District #1 Open House Scheduled

More...

January 11th, 2013Influenza Advisory

It's flu season. Prevent it. Treat it. Don't spread it.

More...

November 9th, 2012Thank You Phoenix Elementary District #1 Community

More...

October 24th, 2012Phoenix Elementary School District #1 Receives ENERGY STAR Leader Rating

District Achieves 20% Energy Efficiency Improvement Goal

More...

October 9th, 2012Annual Notice Regarding Destruction of Education Records

More...

October 2nd, 2012Herrera School Congratulates Ms. Carmen Sanchez Gore

2012 Esperanza Latino Teacher Recipient

More...

October 2nd, 2012October Community Newsletter

More...

September 10th, 2012Edison School Creates Electromagnetic Spectrum Themed Art

More...